| Work Plan 2007/2008 | ||||||
| I. Genreal Coordination | ||||||
| Area of Work | Activity | Participants | Responsible Entities | Output | Deadline | |
| 1. | Financial and office management | Maintenance of the office and financial management system as well as the further development of the general administrative practices of the secretariat | BSC PS | BSC-PS | Office fully operational | Continuous |
| 2. | Integration of scientific findings of Black Sea projects in the work of the Black Sea Commission | Participation in meeting and seminars of regional projects (end-user of ASCOBOS, SESAME, SCENE, HERMES, MATRA, PlanCoast); New EU Projects were developed - with EU-Consult, CEFAS - positive evaluation for the moment. | BSC PS, EC DG Research, BSERP | BSC PS | Meetings' records, data | Continuous |
| Input of relevant information into BSC Black Sea Information System | ||||||
| 3. | Operation of the Black Sea Information System and GIS | Current operation of the BSIS | EC DG Env | BSC PS | BSIS (including GIS interface) is operational at BSC/PS office | Continuous |
| Development of BSIS in ACCESS Format (mdb), on-line nurishing of the data base. | BSERP, BSC PS | BSC PS | ||||
| 4. | Coordination of the Black Sea Institutional and Expert Network | Support the work of the expert networks; establish expert groups on issues that require in depth studies and attraction of wider scientific expertise; establishment of discussion fora, documents database, contact lists, etc. based on their needs | BSC PS, EC DG Env, GESAMP, others on an ad hoc basis | BSC PS | Minutes of meetings, presentations, reports if produced | Continuous |
| 5. | Expanding the cooperation with international organizations of relevance through joint activities or shared expertise. | Setting up or strengthening the cooperation arrangements with EC DG Env, BSEC, PABSEC, UNEP (GPA; Regional Seas), EC DG JRC, OSPAR, MAP, HELCOM, ESPOO Convention, EUROGOOS, Ballast Water Convention, London Convention, UNDP (Test Projects), OSCE, GESAMP, IMO, SIDA, SMA, EMSA, EEA, WHO, etc.; organize joint events when appropriate | BSC PS, Organisations mentioned | BSC PS | Proceedings of meetings with participation of BSC reps. in meetings, conferences | Meetings calendar |
| Representing the Commission at meetings, conferences, workshops and other fora, presentations, delivering lectures, reports, etc. Raising awareness of the activities of the Commission. | ||||||
| 6. | Implementation of the MOU between the BSC and the ICPDR | Report (information exchange) to the Both BSC and ICPDR on Danube Impact on the Black Sea | BSC PS, ICPDR | BSC PS | Reports | Aug-08 |
| Meetings of Black Sea –Danube JTWG: Process of achieving agreed opinion on nutrient status of the Danube and NW Black Sea. | ICPDR | Upon availability of funding | Jun-08 | |||
| 7. | Implementation of the MoU with the EEA and the proposed work plan under this MoU | Indicator-based report on Pressures and Trends in the State of the Environment and Annual Reporting to the Commission, for 2007/8. | BSC PS, EEA | BSC PS | Report | Dec-08 |
| Improvement of BSIS with EEA assistance. Meta data base: what is available in the region, but not reported to the BSC | Meta database | Dec-08 | ||||
| Ensure regular flow of data between two institutions | data exchange | Continuous | ||||
| 8. | Implementation of the Memorandum of Cooperation between the BSC and ACCOBAMS | Performing the functions of ACCOBAMS Sub-regional Coordinating Unit. | ACCOBAMS Secretariat | BSC PS | Report(s) | Dec-08 |
| Pilot Project Marine Litter/Marine Mammals. | ACCOBAMS and UNEP | Report | Dec-08 | |||
| Support to the Project 'Development of Black Sea Cetaceans Stranding Network' (funded by ACCOBAMS). | NGO's and ACCOBAMS | Report | Dec-09 | |||
| Incorporation of the Marine Mammals Conservation Plan into the SAP2007. | ACCOBAMS | Inclusion in the new SAP | May-08 | |||
| 9. | Involvement of the private sector in the implementation of the BS SAP | Development of cooperation mechanism with the private sector | OSPRI; MEKE etc | BSC PS | Meeting minutes | Continuous |
| 10. | Preparation of Ministerial Meeting 2008 | Preparation of Meeting Program and coordination of preparatory work to the Ministerial Meeting 2008 | EC, BSERP, EuropeAid, BSC PS | Government of Ukraine | Meeting Program negotiated and adopted Technical
docs for the Ministerial Meeting (2008) Technical document for national
negotiations |
Jun-08 |
| 11. | SOE Report 2000-2005 | Finalization of the preparation of the State of Black Sea Environment (SOE) | BSERP, IAEA | BSC PS | Report | Dec-07 |
| 12. | Updating of the BSSAP | Report on the Implementation of the BS SAP Report | BSC PS | BSC PS | Report | May-08 |
| Finalization of the GAP Analysis Report | EC DG Env, TUBITAK | Regional GAP Analysis Report | Sep-07 | |||
| Finalization of the BSSAP for National Negotiations | BSERP | BSERP | Technical SAP 07 | Jan-08 | ||
| Politically negotiated SAP 07 | Apr-08 | |||||
| 13 | Updating of the Convention and related documents | Amendments to the Convention | EuropeAid, BSC PS | Europaid, Beneficiary countries | Proposal for amended text of the Convention | Oct-08 |
| Amendments to other Convention related documents (Financial Rules, Headquarters Agreement, Privileges and Immunities Agreement) | BSC PS | BSC | Draft proposal texts of amendments | |||
| Amendments to basic documents of the Black Sea Commission | BSC PS | BSC | Jun-08 | |||
| 14 | Operative management | Meetings of the AG of the BSC (1 meeting for each AG), Experts Workshops | BSC PS, BSERP | BSC PS | Minutes of Meetings Meeting documents, presentations, etc., significant progress in the preparation of the Meeting of the Contracting Parties, Kyiv 2008 |
Different dates |
| Regular meeting of the Black Sea Commission | ||||||
| Extraordinary Meeting(s) of the Black Sea Commission | ||||||
| II Policy Actions | ||||||
| Area of Work | Participants | Responsible Entities | Output | Deadline | ||
| Pollution Reduction | ||||||
| 1. | Work on the environmental quality objectives and target values | Assessment of background levels of pollution using the collected historical data, information/data on pressures and trends, continued | BS scientific community, AG | BSC PS, PMA AC | Reports on Pilot Monitoring exercises. Report on trace metals and other pollutants background values | Oct-08 |
| 2 | Harmonisation of methods, standards | Regional Guidelines on Trace Metals identification in Water, Sediments and Biota | BS scientific community, AG | PMA AC, IAEA, BSC PS | 1. Adopted Guidelines, 2. Report | Sep-08 |
| Harmonization of pesticides methods, standards | ||||||
| Report on the use of Black Sea Manuals and Intercalibration Exercises | ||||||
| 2. | Implementation and improvement of the BS Integrated Monitoring and Assessment Programme (BSIMAP) | QUASIME: mandatory QA/QS for laboratories reporting to BSIMAP and financed from BSC budget | BSC PS, Laboratories | BSC PS | Reports on inter-comparison exercises, results of analysis of sediment samples collected during Pilot Monitoring exercises; Adopted UNEP ML Guidelines | Oct-07 |
| IAEA Intercomparison exercise for trace metals in biota | Laboratories from the Black Sea coastal states | Laboratories from the Black Sea coastal states | ||||
| Introduction of marine litter component in BSIMAP: initial Steps; Adoption of UNEP Guideline (when published) | UNEP | BSC PS, PMA AG | Sep-08 | |||
| Development of indicator-based reporting on trends using EEA and HELCOM experience | EEA, HELCOM | BSC PS | ||||
| Application of Phytoplankton, Zooplankton, Benthos Manuals for the Black Sea , harmonized approach to sampling and processing of biological samples | BS scientific community, AG | Intercomparison exercises, Overview of results | Continuous | |||
| 3. | Enhancing cooperation with the London Convention and improvement of ESAS reporting on dumping | Romanian Guideline on Dregded materials and IMO Guideline on management of wastes to be adopted | Invite IMO, London Convention, BS countries | BSC PS, ESAS, PMA AGs | Updated reporting formats of ESAS | Oct-08 |
| 5. | Assessment of bathing water quality | Improvement of the regular reporting to the BSC on the bathing waters quality | BSERP, WHO | BSC PS, PMA AG | Report on the workshop of experts and PMA AG on bathing waters; Indicator-based information on complience of bathing water quality with guide and mandatory standards | Oct-08 |
| Communication of bathing waters related information on the BSC website. | Nov-08 | |||||
| 6. | Assessment of the measured pollution inputs (municipal and riverine) | 1) Finalization and adoption of “Hot Spots” criteria and guidelines for including and excluding of sources of pollution from the regional list of Hot Spots | BSERP | LBS AG And AC | Apr-08 | |
| 2) Initiate regular updating the list of hot spots for the Black Sea based on agreed criteria. Meta data of industrial and municipal sources monitored in the region. Designation of new Hot Spots. | LBS AG And AC | continuous | ||||
| 3) List of priority substances to be monitored for rivers: harmonization of monitoring strategies in the region. | BSC PS, LBS AG and AC | Jun-08 | ||||
| 8. | LBS Pollution Control | 1. Finalize the revision of the LBS Protocol and facilitate the process of national negotiations in view of the Ministerial Meeting. (continued) | BSERP, UNEP | BSERP, UNEP Team, LBS AG and AC, BSC PS | Final draft of LBSA Protocol to the Bucharest Convention based on results of 6 national workshops | May-07 |
| 2. Adressing difuse sources of pollution in the Black Sea | BSC PS, IFIs | LBS AG and AC, BSC PS | Project Concept | Sep-08 | ||
| 4. Harmonization of standards for emmissions and discharges to be authorised (point sources) | BSC PS, LBS AG, AC | Progress Report | ||||
| 5. Measured discharges: overview and further steps for harmonization of monitoring strategies (rivers) | ||||||
| 6. Indicator-based reporting on pressures | BSC PS, EEA | Indicator Data | ||||
| 9. | Marine litter reduction | Incorporation of the ML Action Plan in the Black Sea SAP, publication of the ML Report, ML/MM Pilot project, Adoption of UNEP Guidelines; International Clean-up day; Development of ML component in BSIS | UNEP, ACCOBAMS | BSC PS, Consultants, PMA AG | Final Reports, upon approval of the project | Dec-08 |
| 10. | Implementation of the BS Contingency Plan | 1. Black Sea DELTA exercise upon availability of a volunteer hosting country | .OSPRI | Black Sea countries | Report on SULH. | Oct-08 |
| 2. Regular Black Sea ALPHA exercises | ||||||
| 3. Qquarterly BS BRAVO Exercises | Black Sea countries | continuous | ||||
| 4) Maintenance and update of the operational information for the implementation of the Contingency Plan | ||||||
| 5. VTOPIS | BSERP, Consultant | Final Report on VTOPIS Pilot Project | ||||
| 6. Update of the annexes to the Contingency Plan and Guidelines for Oil Spill Exercises | BSC PS | AG ESAS | Approval by Commissioners | Dec-08 | ||
| 7. Preparation for signature by remaining countries | BSC PS | Signing by countries | Jun-08 | |||
| 12 | 8. SAR Training Project | SIDA, IMO, BSC PS, BS countries SAR Authorities | Project Proposal, (if accepted) training | Dec-08 | ||
| 11 | SIDA Project | Finalization of the project proposal | BSC PS, HELCOM, SIDA, ESAS AC | BSC PS | Project proposal | Nov-07 |
| Increased coopeation with HELCOM | BSC PS, BSC, IMO, ESAS & CBD AGs, SIDA/HELCOM | Reports, Meeting documents, Database, etc. | Dec-09 | |||
| 1 – Development and Implementation of a Black Sea Strategy for port reception facilities and database for ship-generated wastes. | ||||||
| 2 – Strengthening the capability to detect illegal oil discharges | ||||||
| 3 - Enhancing preparedness to effectively respond to medium and major accidents resulting in oil pollution at sea and development of Automatic Information System (AIS) data exchange network between the Black Sea countries to increase the safety of shipping in the region | ||||||
| 4 – Facilitation of harmonized implementation and ratification of the BWM Convention by the Black Sea countries and elaboration of a road map for the Black Sea | ||||||
| B. Management of Living Resources | ||||||
| 11. | BS Biodiversity Assessment | 1) Continuation of the work on the of habitat classification and mapping | EEA, BSC PS, CBD and FOMLR Ags, others | BSC PS, CBD and FOMLR AGs | ||
| 2) Fascilitate the designation of MPAs in the region | BSC PS, Black Sea countries | MPAs | Continuous | |||
| 3) Upgrade of the methodological basis for biological studies (e.g jellyfish) | BSC PS, CBD AG | Methodology | Nov-08 | |||
| 12. | Conservation of the Black Sea cetaceans | Fundraising for regional assessment of abundance and distribution of the Black Sea cetaceans - still necessary | Private Sector | BSC PS | continuous | |
| Enhancing Black Sea cetacean stranding network | ACCOBAMS | Jan-08 | ||||
| 13. | Support to the process of negotiation on the Black Sea Legally Binding document on fisheries | Participation in a Joint Meeting of DG FISH, DG ENV and the Black Sea countries. | BSERP, EC TAIEX, DG FISH,DG ENV | Meeting Minutes | Mar-08 | |
| Continuing of the work towards convergence of the positions of the Black Sea countries on LBD | Modifcations in the Legally Binding Document on fisheries as necessary | |||||
| 14. | Increasing the knowledge on fisheries management in the Black Sea | Cooperation in fishery assessment with various related organizations | FAO, GFCM, Instituions in the Black Sea countries, DG FISH, DG ENV | BSC PS | Upon availability of funding / continuous | |
| 15. | Restoration of areas vital to the recovery of Black Sea fish stocks. | 1) habitat mapping for fish species listed in Annex IV of the Biodiversity Protocol: continued | BSERP | BSC PS | Technical reports and maps | Jan-08 |
| 2) Development of the fisheries indicators in the Black Sea | Sep-08 | |||||
| 16. | Preventing the introduction of exotic species | Improvement of the national reporting on exotic species (continued) | National CBD Focal Points | Information submitted to the Secretariat | Continuous | |
| Indicator-based reporting | Biological indicators of biodiversity response to pollution. | PMA, CBD AGs, voluntary scientific teams | List of indicators and Methodology | Continuous | ||
| Update/Amendment of SAP2007. | Drafting the Technical SAP | BSERP, Consultants, BSC PS, BS countries, National Represenatatives | BSERP | Technical SAP 07 | Jan-08 | |
| Politically negotiated SAP | BSERP, Consultants, BSC PS, BS countries, National Represenatatives | Politically negotiated SAP | Apr-08 | |||
| C. Sustainable Human Development | ||||||
| 17. | Development of a procedure for EIA in Transboundary Context | 1) Consultative meeting with Espoo Convention | Espoo Convention | BSC PS, ESPOO Convention | BS Guidance | Oct-08 |
| 2) Preparation of BS regionalGuidance on EIA in transboundary context | ||||||
| 18. | Implementation of ICZM and enhancing cooperation with EUROPEAID Project | 1) ICZM Guidelines: initial steps | BSERP | ICZM AG, BSC PS | Report on Feasibility study Meeting Docs, Report Docs of the Regional ICZM workshop, Regional Assessment of the ICZM Qusetionnaires; Report on the Akcakoca Pilot Project, Erosion Project Proposal; Ministerial Declaration with ICZM component, ICZM Guidelines for implementation of the ICZM Strategy |
Oct-08 |
| 2) ICZM in the Ministerial Declaration | EuropAid | |||||
| 3. Development of ICZM assessment methodologies and a system of indicators for the evaluation of the status of the coastal zone (continued) | May-08 | |||||
| 4. ICZM Progress markers application in the region (Methodology developped by EUCC-the Coastal Union) | ||||||
| 5. Incorporation of the BS ICZM Strategy in the SAP2007 | SAP Formulation Team, ICZM AG | |||||
| 6. Pilot Project Akcakoca follow up | Plan Coast | |||||
| 7. Erosion Project Proposal | EU-CONSULT | |||||
| 19. | Promote region-wide cooperation in the investment sector | Participation in DABLAS Task Force. | BSERP, EC DGE | BSC PS, BSERP, Consultant | Significant progess in the development af
bankable projects in the BS, Database updated |
|
| Promotion of priority investment projects taking into consideration the regional impact | ||||||
| Update the DABLAS database | ||||||
| 20. | Convergence of the principles of the EU Water Framework Directive and the activities of the Commission | Continuation of the work on the applicability of the WFD Implementation Guidelines in the BS area | BSC PS, BSERP | Meeting documents | Dec-08 | |
| 21. | Enhancing public awareness of the Bucharest Convention and BS SAP. Increasing the public participation in the Black Sea process. | 1) Maintenance of the public section of the BSC website | BSERP, EC, NGO, Private Sector, BSC PS, etc. | BSC PS, BSERP | as per activity | continuous, as per activity where applicable |
| 2) Publish newsletter Saving the Black Sea | ||||||
| 3) Coordinated public awareness campaigns (with NGOs- ) | ||||||
| 4) International Black Sea Day, Maintenance of the BS Day Website | Report on activities | |||||